How to Replenish Oil Leakage in Oil Immersed Transformers
Nov 14, 2023
How to Replenish Oil Leakage in Oil Immersed Transformers
1. Stop the transformer in operation and take safety measures such as power outage and locking; 2. The transformer oil used must meet the standards and should be checked for quality assurance; 3. Electrical test reports should be reviewed; 4. After refueling, it is necessary to let it sit for a period of time before putting it into operation, and observe for a period of time after putting it into operation.
Regarding the issue of mixed oil in transformer oil, the national standard GB/T14542-2017 shall prevail, and the excerpts are as follows:
When oil products need to be mixed for use, the participating oil products should meet their respective quality standards (new oil should meet the new oil quality standards, and operating oil should meet the operating oil quality standards).
When electrical equipment needs to be refilled due to insufficient oil filling, oil products of the same oil base, brand, and additive type should be added. Unused transformer oil that meets the GB2536 standard or used transformer oil that meets the GB/T7595 operating oil quality standard should be selected, and the characteristic indicators of the refueling product should not be lower than the oil inside the equipment. When there is a large amount of oil replenishment (greater than 5%), a sludge precipitation test of the mixed oil should be conducted before refueling to confirm that there is no sludge precipitation, acid value, and medium loss factor lower than the oil in the equipment before refueling.
3. Oils with different oil bases, grades, and additive types should not be mixed in principle. In special circumstances, if different grades of new oil need to be mixed for use, the suitability for use in the region should be determined based on the measured pour point of the mixed oil (the pour point should refer to the pour point index of GB2536 New Transformer Oil), and then an open cup aging test should be conducted according to the DL/T429.6 method. After aging, the mixed oil should have no oil sludge precipitation, and the acid value and dielectric loss factor of the mixed oil should not be worse than the worst single oil sample.
4. If different grades of new oil or used oil are mixed into the operating oil, in addition to measuring the pour point of the mixed oil in advance (the pour point should refer to the pour point index of GB2536 New Transformer Oil), the following requirements should also be met:
a) The various characteristic indicators of the added oil should not be lower than the oil in the equipment, and the quality of the mixed oil should not be lower than the operating oil;
b) Open cup aging test should be conducted for operating oil, supplementary oil, and mixed oil according to DL/T429.6 method. After aging, the mixed oil should have no oil sludge precipitation, and the acid value and medium loss factor of the mixed oil and supplementary oil should not be greater than the measured results after aging of the operating oil.
When conducting a mixing test, the mixing ratio of the oil sample should be the same as the actual proportion used; If the oil to oil ratio cannot be determined, a 1:1 mass ratio mixture is used for testing
PRODUCT LINK
http://www.switchgear-china.com/power-distribution-transformer/oil-immersed-transformer/low-noise-10-kv-electrical-power-transformer.html
PRODUCT PHOTO








This product is usually customized.
We are a manufacturer and have a professional technical department that can design and provide solutions according to customer needs.
Please click on the button below to send us the information, and our sales personnel will contact you to provide you with the design drawings
Here are our customer examples for your reference
Uzbekistan customer
Data sheet N° 2-A: Transformer H61 33 kV/400V of 160 kVA
|
DESIGNATIONS |
S UNITS |
SPECIFIC DATA |
CANDIDATE DATA |
|
Maker |
|
To be indicated |
|
|
Reference standard |
|
IEC 60076 |
|
|
Type |
|
Phase |
|
|
Vat |
|
Hermetic |
|
|
Execution |
|
Tropicalized |
|
|
Dielectric |
|
PCB-free oil |
|
|
Installation |
|
On pole |
|
|
Operating ambient temperature |
°C |
45 |
|
|
Rated frequency |
Hz |
50 |
|
|
Rated power |
Kva |
160 |
|
|
Rated primary voltage |
Kv |
33 |
|
|
Isolation level assigned to primary school |
Kv |
36 |
|
|
Number of phases in primary school |
|
03 |
|
|
Secondary voltage |
V |
400/230 |
|
|
Voltage adjustment range on the M side when unladen |
% |
±2.5 |
|
|
Coupling |
|
Yzn11 |
|
|
Short circuit voltage |
% |
4 - 4.5 |
|
|
Neutral sized for one load |
% |
100 |
|
|
Maximum vacuum losses |
W |
230 – 460 |
|
|
Losses due to Maxi load |
W |
1450 - 2350 |
|
|
Maximum steady-state oil temperature |
°C |
55 |
|
|
Maximum temperature of the windings in steady state |
°C |
60 |
|
|
Winding material |
|
Electrolytic copper |
|
|
Maximum noise level |
Db |
52 |
|
|
50Hz industrial frequency hold, 1 min |
Kv |
50 - 70 |
|
|
Shock wave resistance (1.2/50 micros) |
Kv |
125 - 170 |
|
|
Cooling |
|
ONAN |
|
|
Nameplate |
|
01 |
|
|
Grounding connection |
|
01 |
|
|
Dimensions Height/width/depth |
mm x mm x mm |
1200 X 1050 X 710 |
|
|
Total mass of transformer including oil |
Kg |
400 |
|
|
Oil mass |
Kg |
90 |
|
|
PAINT |
|
||
|
|
|
Tropicalized and anti-rust |
|
|
|
|
Layers |
|
|
|
|
Binder |
|
|
|
|
Colour |
|
|
|
|
Plans and technical diagrams to be provided. |
|
IF NEED MORE DETAILES,PLEASE FEEL FREE YO CONTACT US